BUILDING PLAN APPROVAL SYSTEM
RGDPS TIMELINE AS PAR RGDPS ACT 30 days
Total Received 12809
Total Approved 7003
Average time taken 27
Median time taken 40
Minimum time taken 0
Maximum time taken 301
LAND CONVERSION 90-A
RGDPS TIMELINE AS PAR RGDPS ACT 90 days
Total Received 1117
Total Approved 0
Average time taken 30
Median time taken 0
Minimum time taken 0
Maximum time taken 168
URBAN DEVELOPMENT TAX
RGDPS TIMELINE AS PAR RGDPS ACT 60 days
Total Received 58
Total Approved 18
Average time taken 57
Median time taken 28
Minimum time taken 2
Maximum time taken 157
MUTATION/ NAME TRANSFER
RGDPS TIMELINE AS PAR RGDPS ACT 7 days
Total Received 25194
Total Approved 15573
Average time taken 37
Median time taken 24
Minimum time taken 1
Maximum time taken 459
FIRE NOC/RENEWAL
RGDPS TIMELINE AS PAR RGDPS ACT 7 days
Total Received 5651
Total Approved 3272
Average time taken 59
Median time taken 38
Minimum time taken 1
Maximum time taken 566
TRADE LICENCE/RENEWAL
RGDPS TIMELINE AS PAR RGDPS ACT 7 days
Total Received 4311
Total Approved 1537
Average time taken 59
Median time taken 33
Minimum time taken 1
Maximum time taken 489
MOBILE TOWER/RENEWAL
RGDPS TIMELINE AS PAR RGDPS ACT 60 days
Total Received 0
Total Approved 0
Average time taken 0
Median time taken 0
Minimum time taken 0
Maximum time taken 0
SIGNAGE LICENCE/RENEWAL
RGDPS TIMELINE AS PAR RGDPS ACT 45 days
Total Received 3
Total Approved 0
Average time taken
Median time taken
Minimum time taken
Maximum time taken
SEWER CONNECTION
RGDPS TIMELINE AS PAR RGDPS ACT 3 days
Total Received 710
Total Approved 37
Average time taken 102
Median time taken 114
Minimum time taken 6
Maximum time taken 372
PROPERTY ID
RGDPS TIMELINE AS PAR RGDPS ACT 45 days
Total Received
Total Approved
Average time taken
Median time taken
Minimum time taken
Maximum time taken
CHANGE OF LAND USE RULES 2010
RGDPS TIMELINE AS PAR RGDPS ACT 60 days
Total Received 4
Total Approved 0
Average time taken 0
Median time taken 0
Minimum time taken 0
Maximum time taken 0
CHANGE OF LAND USE RULES 2012
RGDPS TIMELINE AS PAR RGDPS ACT 45 days
Total Received 13
Total Approved 0
Average time taken 0
Median time taken 0
Minimum time taken 0
Maximum time taken 0
E- INTIMATION FOR PLINTH LEVEL INSPECTION
RGDPS TIMELINE AS PAR RGDPS ACT 90 days
Total Received 0
Total Approved 0
Average time taken 0
Median time taken 0
Minimum time taken 0
Maximum time taken 0
E- INTIMATION FOR COMPLETION OF CONSTRUCTION
RGDPS TIMELINE AS PAR RGDPS ACT 90 days
Total Received 0
Total Approved 0
Average time taken 0
Median time taken 0
Minimum time taken 0
Maximum time taken 0