BUILDING PLAN APPROVAL SYSTEM
RGDPS TIMELINE AS PAR RGDPS ACT 30 days
Total Received 10408
Total Approved 5459
Average time taken 25
Median time taken 43
Minimum time taken 0
Maximum time taken 292
LAND CONVERSION 90-A
RGDPS TIMELINE AS PAR RGDPS ACT 90 days
Total Received 1030
Total Approved 0
Average time taken 26
Median time taken 0
Minimum time taken 0
Maximum time taken 168
URBAN DEVELOPMENT TAX
RGDPS TIMELINE AS PAR RGDPS ACT 60 days
Total Received 54
Total Approved 16
Average time taken 49
Median time taken 24
Minimum time taken 2
Maximum time taken 157
MUTATION/ NAME TRANSFER
RGDPS TIMELINE AS PAR RGDPS ACT 7 days
Total Received 20679
Total Approved 12363
Average time taken 35
Median time taken 25
Minimum time taken 1
Maximum time taken 366
FIRE NOC/RENEWAL
RGDPS TIMELINE AS PAR RGDPS ACT 7 days
Total Received 4031
Total Approved 2115
Average time taken 57
Median time taken 37
Minimum time taken 1
Maximum time taken 484
TRADE LICENCE/RENEWAL
RGDPS TIMELINE AS PAR RGDPS ACT 7 days
Total Received 3566
Total Approved 1266
Average time taken 54
Median time taken 32
Minimum time taken 1
Maximum time taken 399
MOBILE TOWER/RENEWAL
RGDPS TIMELINE AS PAR RGDPS ACT 60 days
Total Received 0
Total Approved 0
Average time taken 0
Median time taken 0
Minimum time taken 0
Maximum time taken 0
SIGNAGE LICENCE/RENEWAL
RGDPS TIMELINE AS PAR RGDPS ACT 45 days
Total Received 3
Total Approved 0
Average time taken
Median time taken
Minimum time taken
Maximum time taken
SEWER CONNECTION
RGDPS TIMELINE AS PAR RGDPS ACT 3 days
Total Received 633
Total Approved 10
Average time taken 70
Median time taken 26
Minimum time taken 6
Maximum time taken 279
PROPERTY ID
RGDPS TIMELINE AS PAR RGDPS ACT 45 days
Total Received
Total Approved
Average time taken
Median time taken
Minimum time taken
Maximum time taken
CHANGE OF LAND USE RULES 2010
RGDPS TIMELINE AS PAR RGDPS ACT 60 days
Total Received 4
Total Approved 0
Average time taken 0
Median time taken 0
Minimum time taken 0
Maximum time taken 0
CHANGE OF LAND USE RULES 2012
RGDPS TIMELINE AS PAR RGDPS ACT 45 days
Total Received 13
Total Approved 0
Average time taken 0
Median time taken 0
Minimum time taken 0
Maximum time taken 0
E- INTIMATION FOR PLINTH LEVEL INSPECTION
RGDPS TIMELINE AS PAR RGDPS ACT 90 days
Total Received 0
Total Approved 0
Average time taken 0
Median time taken 0
Minimum time taken 0
Maximum time taken 0
E- INTIMATION FOR COMPLETION OF CONSTRUCTION
RGDPS TIMELINE AS PAR RGDPS ACT 90 days
Total Received 0
Total Approved 0
Average time taken 0
Median time taken 0
Minimum time taken 0
Maximum time taken 0