Live Statistics Data Updated as on: 13-09-2024 01:06:36

TRADE LICENCE/RENEWAL
RGDPS TIMELINE AS PAR RGDPS ACT 7 days
Total Received 8192
Total Approved 3084
Average time taken 87
Median time taken 35
Minimum time taken 1
Maximum time taken 1110
FIRE NOC/RENEWAL
RGDPS TIMELINE AS PAR RGDPS ACT 7 days
Total Received 24867
Total Approved 14745
Average time taken 68
Median time taken 43
Minimum time taken 1
Maximum time taken 1218
MUTATION/ NAME TRANSFER
RGDPS TIMELINE AS PAR RGDPS ACT 7 days
Total Received 80363
Total Approved 51315
Average time taken 58
Median time taken 31
Minimum time taken 1
Maximum time taken 1121
SEWER CONNECTION
RGDPS TIMELINE AS PAR RGDPS ACT 3 days
Total Received 2602
Total Approved 738
Average time taken 368
Median time taken 460
Minimum time taken 1
Maximum time taken 929
SIGNAGE LICENCE/RENEWAL
RGDPS TIMELINE AS PAR RGDPS ACT 45 days
Total Received 3
Total Approved 0
Average time taken
Median time taken
Minimum time taken
Maximum time taken
URBAN DEVELOPMENT TAX
RGDPS TIMELINE AS PAR RGDPS ACT 60 days
Total Received 21250
Total Approved 20
Average time taken 121
Median time taken 50
Minimum time taken 2
Maximum time taken 1057
BUILDING PLAN APPROVAL SYSTEM
RGDPS TIMELINE AS PAR RGDPS ACT 30 days
Total Received N/A
Total Approved N/A
Average time taken N/A
Median time taken N/A
Minimum time taken N/A
Maximum time taken N/A
LAND CONVERSION 90-A
RGDPS TIMELINE AS PAR RGDPS ACT 90 days
Total Received N/A
Total Approved N/A
Average time taken N/A
Median time taken N/A
Minimum time taken N/A
Maximum time taken N/A
MOBILE TOWER/RENEWAL
RGDPS TIMELINE AS PAR RGDPS ACT 60 days
Total Received 0
Total Approved 0
Average time taken 0
Median time taken 0
Minimum time taken 0
Maximum time taken 0
PROPERTY ID
RGDPS TIMELINE AS PAR RGDPS ACT 45 days
Total Received
Total Approved
Average time taken
Median time taken
Minimum time taken
Maximum time taken
CHANGE OF LAND USE RULES 2010
RGDPS TIMELINE AS PAR RGDPS ACT 60 days
Total Received N/A
Total Approved N/A
Average time taken N/A
Median time taken N/A
Minimum time taken N/A
Maximum time taken N/A
CHANGE OF LAND USE RULES 2012
RGDPS TIMELINE AS PAR RGDPS ACT 45 days
Total Received N/A
Total Approved N/A
Average time taken N/A
Median time taken N/A
Minimum time taken N/A
Maximum time taken N/A